TOKYO – JFE Steel Corporation today announced its capital investment plan for the fiscal year ending March 31, 2008.
| (in billions of yen) | FY ending March 2008 (planned) |
FY ended March 2007 (estimated) |
Year-on-year % change |
| Construction costs Outlays |
135.0 150.0 |
132.8 116.1 |
2% 29% |
| Works/project | Construction period | Total cost |
|---|---|---|
| Chita Works: Expansion of capacity of medium- diameter seamless pipe mill |
July 2007 – July 2008 | 15.0 billion yen |
| East Japan Works: Construction of scrap-melting shaft furnace at Keihin |
June 2007 – Aug. 2008 | 10.0 billion yen |
| West Japan Works: Construction of coke dry quenching (CDQ) facility at Kurashiki |
July 2007 – Feb. 2009 | 9.5 billion yen |
| East Japan Works: Construction of continuous pickling line at Keihin |
Jan. 2006 – May 2007 | 13.0 billon yen |
| East Japan Works: Construction of No.14 oxygen plant at Chiba |
July 2006 – Aug. 2007 | 6.0 billion yen |
| Years ended (ending) March 31: |
Construction costs |
Outlays |
|---|---|---|
| (in billions of yen) | ||
| 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 (estimated) 2008 (planned) |
228.7 206.4 120.4 122.8 136.2 74.3 85.0 101.4 92.4 101.0 112.0 139.6 132.8 135.0 |
263.7 175.9 122.3 139.2 153.9 88.1 82.1 86.3 88.8 81.7 125.0 109.8 116.1 150.0 |